Specification:
1、In the flow chart of examination and approval procedures
for capital constructions, the work involving the government
is shown in the rectangle frames, and that of construction
unit is shown in the elliptic frames.
2、The arrow direction in the flow chart only represents
the sequence in the examination and approval process and
does not represent the item before the arrow as a necessary
condition of the item after the arrow. The material needed
in each item shall take the content listed in the corresponding
notification as the standards.
Note:
1、Whether the pre-evaluation of safety and sanitatin
is carried out should be determined by related authorities
according to the relevant stipulations of the Decree
(1998) No. 10 of the Ministry of Labor,Procedures on
Administration of Pre-evaluation of Labor Safety and
Sanitation of Construction Project(Engineering).
2、The processing time limit for examination and verification
of bidding documents and of bid-evaluation measures
is within two workdays;other examination and verification
should be conducted immediately.
3、The evaluation and comment on preliminary design shall
be dealt with in different ways according to the examination
and approval grade of a project;1)Important projects
shall be evaluated by experts organized by an engineering
project consulting company with appropriate qualification,
which is designated by the Planning & Construction
Department, SCIP Adminstration Committee. The department
shall make a reply within 10 workdays since receiving
the evaluation opinion of the consulting company and
experts.2) General projects shall be evaluated by experts
organized by the Planning & Construction Department
and a reply shall be made within 10 workdays.3)Simple
projects shall have the reply of the Planning &
Construction Department within 5 workdays.
4、In the whole process of bidding for construction work,
the following time is neccessary:
①The proclamation of bidding notice shall be no less
than 5 workdays.
②The open application shall be no less than one day
③The time period from sending out bidding documents
to opening bids shall be no less than 20 workdays.
|